Riverside Fleet Service Center — Phase 2
AI-assisted quantity survey · Resend delivers bid packages when a client email is provided.
Total estimated material
$68,490
Direct material before markup
Total labor hours
412.5 hrs
Labor cost $45,375
Suggested winning bid
$128,400
Riverside Fleet Service Center — Phase 2
Previewing sample fleet electrical takeoff. Drop your own PDF to run live gpt-4o parsing (requires OPENAI_API_KEY and database).
Blueprint upload
Drag & drop commercial blueprints here
Sheet sets, risers, and details for electrical, plumbing, HVAC, or roofing scopes. Up to 25MB per file.
Takeoff results
Commercial electrical rough-in and gear scope derived from sheet E1–E4. Assumes 85% drawing completeness; verified panel schedule A3.
| Category | Description & specs | Qty & unit | Material | Labor hrs | Line total |
|---|---|---|---|---|---|
Distribution | 800A switchboard, 3PH, NEMA 1, 42-circuit Unit cost $18,400.00 · 18.0 hrs / unit | 1 EA | $18,400.00 | 18.0 hrs | $22,300.00 |
Conduit | 3/4" EMT homerun — office lighting zones Unit cost $2.45 · 0.0 hrs / unit | 2840 LF | $6,958.00 | 39.8 hrs | $9,820.00 |
Devices | 20A duplex receptacles, spec BR-204 Unit cost $28.00 · 0.3 hrs / unit | 186 EA | $5,208.00 | 65.1 hrs | $9,850.00 |
Lighting | 2x4 LED troffer, 40W, 4000K, cat. L-12 Unit cost $118.00 · 1.1 hrs / unit | 124 EA | $14,632.00 | 136.4 hrs | $17,940.00 |
Feeders | #2/0 cu THHN feeder w/ PVC underground Unit cost $12.80 · 0.1 hrs / unit | 640 LF | $8,192.00 | 51.2 hrs | $12,480.00 |